Handwritten or Blurry Delivery Dockets: How to Use Them for Emissions Data

A handwritten or blurry docket still counts if someone can read the quantity, product and date and tie it to a delivery. Here is how to sort the readable ones from the rest, where the backup copy usually sits, and how to estimate and label what nobody can read.

Carbonly.ai Team November 20, 2026 8 min read
Scope 3Scope 1Construction EmissionsDelivery DocketsData QualityAudit Trail
Handwritten or Blurry Delivery Dockets: How to Use Them for Emissions Data

Yes, you can use a handwritten or blurry delivery docket for emissions data. The test is traceability. If someone can read the quantity, the unit, the product and the date, and tie it to a delivery on your invoice, it is usable. For the dockets nobody can read, get a copy from the supplier's records first. Estimate only what is left, and label it.

Most dockets on a construction project were never designed to be carbon records. They were written to prove a truck arrived. So they get rained on, folded into a ute's glovebox and photographed at an angle in bad light.

We build carbon accounting software that reads supplier documents, and poor-quality dockets are where most of the review effort goes. This post covers how to sort a pile of bad dockets, where the backup copy usually sits, and how to treat the gap that remains.

What a docket has to show before you can use it

A delivery docket earns a place in your emissions figures when it carries five facts. You need the quantity, the unit, the product, the delivery date and something that ties it to your project or site.

The docket number is a sixth fact, and a useful one. It is the key that matches the docket to the supplier's invoice and statement.

Neatness doesn't matter. A docket written in biro by a driver is fine if the numbers can be read with confidence. A crisp printed docket is useless if the quantity field is torn off.

Sort the pile into three groups

Before anyone types a number, split the dockets into three groups. This takes less time than it sounds, and it stops one bad docket holding up the rest.

Readable. Every one of the five facts can be read without guessing. These go straight into your figures.

Partly readable. Some facts are clear and one is not. The quantity reads "24.?" or the product code is smudged. Two readers might write down different numbers. These need a second source before they count.

Unreadable. The quantity can't be read at all, or the docket is missing. These need a replacement copy or an estimate.

Write down which group each docket went into and why. An assurer will ask how you handled poor-quality records. A short register with the docket number, the problem and the fix answers that question.

Where the backup copy usually sits

The paper docket in your folder is rarely the only record of the delivery. Ask where else the quantity was written down.

The supplier's invoice or statement. Many concrete, quarry and fuel suppliers list docket numbers and quantities on the invoice. If the docket number is readable, the invoice often gives you the quantity.

The supplier's dispatch system. Batching plants and quarries usually print dockets from a dispatch or weighbridge system. A request for a reprint or a delivery report for your project and period is a normal accounts query.

Fuel card and refueller statements. For diesel, the fuel card export or the mobile refueller's monthly statement often holds the same litres as the handwritten bowser docket.

Site records. Daily site diaries, pour records and plant registers sometimes note what arrived. Treat these as a cross-check rather than the primary record.

A replacement copy from the supplier's own system is better evidence than your best reading of a smudged original. File it with the original and note the swap in your register.

Check the partly readable ones against a second source

For a partly readable docket, don't pick the most likely reading and move on. Compare it with the invoice line or statement that covers the same delivery.

If the invoice shows 24.6 m3 against that docket number, and the docket reads "24.?", use 24.6 and note the source. If the two disagree, the invoice is usually the stronger record, because it was generated from the supplier's system. Our post on duplicate invoices inflating carbon numbers covers what to do when two documents describe the same delivery with slightly different quantities.

A smudged product code needs the same treatment. 32 MPa and 40 MPa concrete carry different emission factors. Confirm the grade from the invoice or the purchase order rather than guessing from the docket.

Estimate the dockets nobody can read, and say so

Some dockets will be lost or unreadable, with no copy anywhere. That gap still has to be filled, and the standards allow for it.

For Scope 3 under AASB S2, paragraph B39 asks for all reasonable and supportable information available at the reporting date without undue cost or effort. Paragraph B57 presumes Scope 3 can be estimated reliably using secondary data and industry averages. Paragraph B47 tells an entity to prioritise primary data, all else being equal.

In our reading, that points to an order of preference for each missing docket:

  1. Supplier invoice quantity. If the invoice total covers the period, subtract the readable dockets. The difference is your best figure for the missing ones.
  2. Average of comparable deliveries. Use the average load for the same product, supplier and site in the same period. A concrete truck from one plant usually carries a similar load each trip.
  3. Spend-based estimate. If you hold only the dollar value, apply a spend-based factor. Our guide to spend-based emissions accounting covers the factor sets.

Label every estimated line as an estimate and record the method. Keep the estimated lines separate from measured ones so you can say how much of the category rests on each.

If the docket is for diesel your own plant burned, the figure may be Scope 1 for NGER. The NGER Measurement Determination sets out the methods for working out fuel quantities. Check the method you report under in the Clean Energy Regulator's guidance before filling a gap with an average.

Stop the problem at the source

In our view, a better photo on the day the docket arrives saves more work than any later fix. A one-page note for site staff is the simplest way to get there.

  • Photograph the docket flat, in daylight, with the whole page in frame.
  • Take one photo per docket.
  • Photograph the top copy before it is torn from the pad, because carbon copies fade.
  • Send it the same day, while the driver's handwriting can still be queried.

It is also worth asking your main suppliers for electronic dockets or a delivery report with each invoice. Many dispatch systems already produce one. Our post on field site data collection covers how to make sending documents easy for site managers.

How Carbonly handles hard-to-read dockets

Carbonly reads supplier invoices, dockets and utility bills in eight file formats, including images and scanned documents. When one invoice carries several dockets, it creates one record per docket.

A line it can't read with confidence goes to a reviewer. So does a unit that can't be converted without an unstated figure, such as cubic metres with no density. The reviewer sees the original document beside the extracted figure, confirms or corrects it, and the record keeps the verbatim line text as evidence.

Every record keeps its source document and the emission factor version used. When an assurer asks where a number came from, the evidence pack links it back to the docket. The document processing overview shows the review step in more detail.

Software doesn't make a missing docket appear. The register, the supplier copies and the labelled estimates above are still your job, and they are what an assurer will test.

FAQ

Can I use a handwritten delivery docket for emissions reporting? Yes, if the quantity, unit, product and date can be read with confidence and the docket ties to a delivery on your invoice. Handwriting is fine. Guessing is the problem, so check unclear figures against the supplier's invoice or statement.

What do I do with a delivery docket nobody can read? Ask the supplier for a reprint or a delivery report from its dispatch system. If no copy exists, estimate the quantity from the invoice total less the readable dockets, or from comparable deliveries. Label the line as an estimate and record the method.

Is the supplier invoice or the docket the better record for emissions? When they disagree, the invoice is usually stronger because the supplier's system generated it. The docket proves the delivery reached your site. Keep both, and note which figure you used and why.

Do estimated quantities from missing dockets affect my AASB S2 disclosure? In our reading, AASB S2 allows estimation for Scope 3, and paragraph B57 presumes it can be done reliably with secondary data. Paragraph B47 asks you to prioritise primary data. So keep estimated lines separate and be ready to say how much of each category they cover.

How do I stop getting blurry docket photos from site? Give site staff a short photo guide. Shoot each docket flat, in daylight and in full frame, one per photo, and send it the same day. Asking suppliers for electronic dockets with each invoice removes most of the problem.

Related reading

Related articles

Supplier invoices turned into Scope 3 line items you can show an auditor

Bring one subcontractor invoice, concrete docket or freight bill. In 30 minutes we show the quantities Carbonly reads from it, the factor or EPD each line matches, and the source document behind every tonne.

Book a 30-minute call Prefer email? hello@carbonly.ai

Per-project pricing, no per-seat fees. We reply within business hours.